Ramskill Martin

  • Training, Seminars, Workshops and Surgeries
  • Risk Reviews
  • Programming and Delay Analyst Services
  • Programming and Planning Services
  • Adjudication
  • Rail
  • Dispute Avoidance
  • Ramskill Martin 10 Year Anniversary

    10 YEARS IN BUSINESS 2002 - 2012

    Construction Contracts Consultants
    Chartered Quantity Surveyors
    Adjudicators

    Articles & Legal Updates – Signup








    Risk Review Prepared for a Ground Worker Specialist Subcontractor


    Type of Project – University Student Accommodation

    RM’s client was a ground worker with an initial subcontract sum of £94k with terms and conditions that were bespoke to the main contractor and riddled with onerous terms and condition precedents. The subcontract was complex and incorporated several sums in the serial based subcontract.

    Description of Issues

    RM was required to prepare a risk review in respect of valuation matters, withholding items and delays.

    Entitlements or Liabilities

    The main contractor had made an informal offer to settle the account with a further payment to cover all outstanding matters in the sum of £90k. The subcontractor’s quantity surveyor was seeking to recover an additional sum of £160k.

    Assistance to the Specialist Subcontractor

    RM’s risk review identified that the claim made by the ground worker was unrealistic and the valuation of any further payment was likely to be £70k.

    RM advised the ground worker to return to the negotiation table and accept the £90k previously offered by the main contractor.

    The specialist subcontractor was also advised that the (CBA) would indicate that no benefit would be achieved by pursuing sums via the adjudication process.

    Monies Involved

    RM’s client returned to the negotiation table and received a further payment of £90k.

    Ramskill Martin

     
    Solutions that make business sense